Preparation before installation

1. Check the valve: Before installing the Threaded Cartridge Valve, carefully check the appearance of the valve for damage, deformation, etc. At the same time, check whether the model and specifications of the valve are consistent with the system requirements.

2. Cleaning work: Make sure that the installation site is clean and free of impurities, oil, etc. Cleaning can be done with detergent and a clean cloth to prevent impurities from entering the system and affecting the normal operation of the valve.

3. Prepare tools: Prepare suitable installation tools such as wrenches, torque wrenches, etc. Ensure the quality and accuracy of the tools to avoid damage to the valve during installation.

Precautions during installation

1. Thread matching: Make sure that the threads of the Threaded Cartridge Valve match the threads of the mounting hole. If the threads do not match, the valve may not be installed firmly or even leak. Before installation, tools such as thread gauges can be used for inspection.

2. Installation direction: Pay attention to the installation direction of the Threaded Cartridge Valve. Generally, there will be an arrow mark on the valve to indicate the flow direction of the fluid. During installation, ensure that the arrow direction is consistent with the flow direction of the fluid in the system to ensure the normal operation of the valve.

3. Tightening torque: Use a torque wrench to install according to the tightening torque specified by the valve manufacturer. Too loose installation may cause leakage, while too tight installation may damage the valve or mounting hole. During the tightening process, the torque should be gradually increased to avoid excessive force at one time.

4. Use of seals: Select appropriate seals according to the requirements of the system. During the installation process, ensure that the seals are installed correctly without damage or deformation. The quality and installation of the seals directly affect the sealing performance of the valve.

5. Avoid external forces: During the installation process, avoid applying external forces to the valve, such as knocking and impacting. These external forces may damage the internal parts of the valve and affect the performance and life of the valve.

Post-installation inspection

1. Leakage inspection: After the installation is completed, a leakage inspection should be performed. You can use pressure testing equipment to pressurize the system and observe whether there is leakage around the valve. If leakage is found, it should be handled in time.

2. Functional test: Before the system is operated, the Threaded Cartridge Valve should be functionally tested. You can manually operate the valve to check whether the valve is opened and closed normally, as well as the valve's response speed.

3. System debugging: During the operation of the system, you should pay close attention to the working status of the Threaded Cartridge Valve. According to the requirements of the system, adjust the valve parameters such as pressure and flow to ensure the performance and reliability of the system.

In short, the installation method of the Threaded Cartridge Valve requires attention to multiple aspects, from preparation before installation to operation during installation, and then to inspection after installation, all need to be strictly followed. Only in this way can the normal operation of the Threaded Cartridge Valve be ensured and the performance and reliability of the system be improved.
×